Timelines

The total project duration is 12 months. The remaining steps in the project are summarised below:

 
January

  • first expert workshop to agree scope of guidance

February

  • development of core content for guidance
  • draft of general guidance

March

  • drafting the guidance document for new and existing buildings and building products

April

  • Begin public consultation
  • Identification of case studies

May

  • Second expert workshop
  • Finalising draft guidance document

June

  • Final draft of guidance document
  • Review by Project Council

July

  • Begin preparation of training materials
  • Finalising guidance document

August

  • Final version of guidance document
  • Completion of case studies

September

  • Report on summary and conclusions from case studies

1st Training course

October

  • 2nd Training course
  • Final dissemination actions